I plan to build some storage schema but I have to anticipate downtime, maintenance and rebuild Time.
Some guys said to me that a 10 disk RAID6 of 10To (SATA) rebuild will last for about a week ! and some company policy ask for stopping activity on Array when rebuilding.
If I use RAID 5 or 6 or 5+1 or 6+1 is there an approximate formula that can give me hint on rebuild time depending on disk size and type (SAS/SATA/SSD). something like rpm x size(Mb) x type-factor x nb-of-disk ...
I would like to be able to anticipate all rebuild time scenario depending on Size/type of RAID/type of Disk.
I know it may depend on hardware quality, but let says I am out of dedicated hardware like 3PAR / STOREWIZE / NETAPP or likes. I am using conventional servers with traditional SAS or SATA drives with software RAID.
社区高分解答
原帖链接 · HBruijn · CC BY-SA 4.0
The theoretical absolute minimum rebuild time is the time needed to write a complete disk worth of data : the capacity of a disk divided by the average sustained write speed a disk can maintain without cache.
(Note: that average sustained write speed will probably be not even near the performance numbers quoted in the specs.)
Larger disks take longer.
Slower disks take longer.
Parity calculations take extra time.
Real world numbers will vary but will certainly be (much) larger and depend on your RAID level , the number of remaining disks, load on the system while the array rebuild takes place, the controller etc.
Also see What are the different widely used RAID levels and when should I consider them?